Revision 1
Over the years we have had different people signing up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.
This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.
The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.
We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2 months long.
During development period, contributors submit patches to be reviewed and committed into xen.git. All feature patches must be committed before a date, which is normally called the “cut-off date”, after which the freeze period starts. There will be a date before which all patches that wish to be merged for the release should be posted – it is normally called the “last posting date” and it is normally two weeks before the “cut-off date”.
During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period.
Here is a conjured up example (use cal 2017
to get an idea):
A trusted developer in the community that owns the release process. The major goal of the Release Manager is to make sure a Xen release has high quality and doesn’t slip too much.
The Release Manager will not see much workload during development period, but expects to see increasing workload during the freeze period until the final release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties and make difficult decisions when necessary.
The Release Manager essentially owns xen-unstable branch during the freeze period. The Committers will act on the wishes of the Release Manager during that time.
A group of trusted developers who are responsible for certain components in xen.git. They are expected to respond to patches / questions with regard to their components in a timely manner, especially during the freeze period.
A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.
Contributors are also expected to respond quickly to any issues regarding the code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.
The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.
The Release Technician is the person who tags various trees, prepares tarball etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.
The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.
They are responsible for coordinating with external reporters to publish Xen release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.
Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Reminders should also be sent one week before important dates (see above, “last posting date” and “cut-off date”). Please consider adding relevant events to your calendar.
Occasionally check the status of the xen-unstable branch, make sure it gets timely pushes to master.
Before or at very early stage of the freeze period, agree with the Community Manager a schedule for RC test days.
Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager. The Release Manager can say “not releasing now” because of too many bugs, “until someone fixes these”, or “no more patches until X, Y, and Z happen”.
Here is a list of things to do for making RCs:
Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.
Send an email to xen-devel, xen-users and xen-announce to announce the RC.
Branch and / or reopen the tree for further feature submission if appropriate.
Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.
When patches to fix issues are posted, determine if the patches are good to be included.
Go back to 1.
It is normally OK in the early RCs that you hand back xen-unstable branch to committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.
At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.
Collate a list of major changes: this should be done in collaboration between Release Manager, PR Personnel and key contributors. This should not be done on a public mailing list, to minimize the risk of release related media stories being published before the release date.
PR Personnel will identify feature highlights, a theme for the press release, companies providing supporting quotes for the press release and media outlets we would want to reach out to and will manage the creation of the press release in private.
The Community Manager will also draft blog post with the help of PR Personnel and Release Manager, which will be published under the name of the Release Manager.
The Community Manager will create release related documentation such as Acknowledgements, Feature List, Man Pages and Release Notes on the wiki accessible via a release category. This can be done in public.
PR Personnel will get stake-holder and Advisory Board approval for the press release (1-2 weeks before the release).
When you think all pending issues are fixed and Xen is ready to be released from the last RC:
Send out commit moratorium emails to committers@.
Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.
Negotiate release date options with PR personnel. Typically we need 3-4 days to line up press briefings with reporters under embargo. PR personnel will also need to consider industry events to ensure that PR is effective. PR releases typically done mid-week (Tuesday - Thursday).
Select the release date.
Check with relevant stake-holders (typically community manager) whether wiki documentation and PR is in good shape (for an example see https://wiki.xenproject.org/wiki/Category:Xen_4.9 https://wiki.xenproject.org/wiki/Category:Xen_4.9)
Obtain a formal go-ahead from
Ask them to dry-run their checklist and confirm everything is OK. If not, arrange another RC and restart this checklist.
Give PR Personnel final go-ahead, and instruct Release Technician to make release deliverables (tags and tarballs - will usually be in place the day before the release). At this point, PR collateral will be sent to reporters (typically 2-3 working days before the release date) and we cannot undo publications without questions being asked and risk of negative PR. It is acceptable to make a xen-devel@ announcement before the PR release date (blog, xen-announce@, press release).
Make the announcement on various mailing list, publish the blog post.
Allow for contingencies. It is not uncommon that some last minute (security or not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting a push. For security bugs, coordinate with the Security Team to adjust the dates according to our security policy.
If there is a new Release Manager for the next release, make sure the following things happen for the new Release Manager.
Note: if you want specific actions from committers, please make sure you CC committers@.
Subject: Xen X.Y rcZ
Hi all,
Xen X.Y rcZ is tagged. You can check that out from xen.git:
git://xenbits.xen.org/xen.git X.Y.0-rcZ
For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz
And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig
Please send bug reports and test reports to xen-devel@lists.xenproject.org.
When sending bug reports, please CC relevant maintainers and me
(abc@xyz.com).
As a reminder, there will be another Xen Test Day.
See instructions on: URL_TO_TEST_INSTRUCTIONS
Subject: No Release Ack needed before RcX
Committers,
The tree is in good state. No release ack is needed before RcX. Please commit
bug fixes at will.
$RM
Subject: Commit moratorium for $REASON
Committers,
Please don't push any new patch to staging because $REASON.
Another email will be sent once the moratorium is lifted.
$RM
Subject: Commit moratorium is lifted for $REASON
Committers,
The commit moratorium is lifted, please commit patches that are already
Release-acked.
$RM
Subject: Last posting date for Xen X.Y is $DATE
Hi all,
The last posting date for Xen X.Y is $DATE. If you want your features to be
included for the release, please make sure they are posted for the first
time before $DATE.
$RM
Subject: Cut-off date for Xen X.Y is $DATE
Hi all,
The cut-off date for Xen X.Y is $DATE. If you want your features to be
included for the release, please make sure they are committed by $DATE.
$RM
Subject: [ANNOUNCEMENT] Xen X.Y is released
Dear community members,
I'm pleased to announce that Xen X.Y.0 is released.
Please find the tarball and its signature at:
https://xenproject.org/downloads/xen-archives/xen-project-xy-series/xen-project-xy0.html
You can also check out the tag in xen.git:
https://xenbits.xen.org/git-http/xen.git RELEASE-X.Y.0
Git checkout and build instructions can be found at:
https://wiki.xenproject.org/wiki/Xen_Project_X.Y_Release_Notes#Build_Requirements
Release notes can be found at:
https://wiki.xenproject.org/wiki/Xen_Project_X.Y_Release_Notes
A summary for X.Y release documents can be found at:
https://wiki.xenproject.org/wiki/Category:Xen_X.Y
Technical blog post for X.Y can be found at:
URL_TO_BLOG
Thanks everyone who contributed to this release. This release would
not have happened without all the awesome contributions from around
the globe.
Regards,
$RM (on behalf of the Xen Project Hypervisor team)
#!/bin/bash
# Use ssmtp for simplicity
# ./status-release.sh | formail -f -s /usr/sbin/ssmtp -bm -t
FILE=`mktemp`
cat << EOF > $FILE
== Hypervisor ==
S: Per-cpu tasklet
O: Konrad Rzeszutek Wilk
E: konrad.wilk@oracle.com
J: XEN-28
=== x86 ===
=== ARM ===
== Completed ==
S:
EOF
AWK_FILE=`mktemp`
cat << EOF > $AWK_FILE
BEGIN { s2_count = 1;score = ""; emails=1; first_time = 1; subject=""}
/== / {
if ( subject != "" ) {
if (score != "")
print "* ", subject, "("score")"
else if (version != "")
print "* ", subject, "("version")";
else
print "* ", subject;
for (i = 1; i <= s2_count; i++) {
if (i in s2)
print " ",s2[i];
}
if (bug != "")
print " Link: https://bugs.xenproject.org/xen/bug/"bug
if (jira != "")
print " - "jira
for (i = 1; i <= count; i++) {
if (i in o)
print " -", o[i]
}
if (emails)
print ""
first_time = 1;
subject=""
email=""
score=""
bug=""
jira=""
version=""
count = 1;
s2_count = 1;
delete s;
delete s2;
delete o;
delete e;
}
print \$0,"\n"
}
/;/ { };
/S:/ {
if ( !first_time ) {
if (score != "")
print "* ", subject, "("score")"
else if (version != "")
print "* ", subject, "("version")";
else
print "* ", subject
for (i = 1; i <= s2_count; i++) {
if (i in s2)
print " ",s2[i];
}
if (bug != "")
print " Link: https://bug.xenproject.org/xen/bug/"bug
if (jira != "")
print " - "jira
for (i = 1; i <= count; i++) {
if (i in o)
print " -", o[i]
}
if (emails)
print ""
}
first_time = 0;
sub(\$1, "");
sub(/^[ \t]+/, "");
subject=\$0;
email=""
bug=""
jira=""
count = 1;
s2_count = 1;
delete s;
delete s2;
delete o;
delete e;
score="";
version="";
}
/O:/ { sub(\$1, ""); o[count++]=\$0; };
/S2:/ { sub(\$1, ""); s2[s2_count++]=\$0;};
/E:/ { sub(\$1, ""); sub(/^[ \t]+/, ""); email=\$0; e[emails++]=\$0;};
/P:/ { sub(\$1, ""); sub(/^[ \t]+/, ""); score=\$0; };
/B:/ { sub(\$1, ""); sub(/^[ \t]+/, ""); bug=\$0; };
/J:/ { sub(\$1, ""); sub(/^[ \t]+/, ""); jira=\$0; };
/V:/ { sub(\$1, ""); sub(/^[ \t]+/, ""); version=\$0; };
END {
}
// { }
EOF
AWK_FILE_EMAIL=`mktemp`
cat << EOF > $AWK_FILE_EMAIL
BEGIN { emails=1;}
/E:/ {
sub(\$1, ""); sub(/^[ \t]+/, "");
email=\$0;
for ( i = 1; i <= emails; i++ ) {
if (i in e) {
if (e[i] == email) {
email="";
break;
}
}
}
if (email != "")
e[emails++]=email;
}
END {
printf "Bcc: "
for ( i = 1; i <= emails; i++ )
if (i in e) {
if (i == emails - 1)
printf "<%s>", e[i];
else
printf "<%s>,", e[i];
}
print ""
}
// { }
EOF
echo "From: $RELEASE_MANAGER_NAME <$RELEASE_MANAGER_MAIL>"
echo "To: xen-devel@lists.xenproject.org"
echo "Cc: $RELEASE_MANAGER_MAIL"
cat $FILE | awk -f $AWK_FILE_EMAIL
rm $AWK_FILE_EMAIL
echo "Subject: Xen $RELEASE_VERSION Development Update"
PRE=`mktemp`
cat << EOF > $PRE
This email only tracks big items for xen.git tree. Please reply for items you
would like to see in $RELEASE_VERSION so that people have an idea what is going on and
prioritise accordingly.
You're welcome to provide description and use cases of the feature you're
working on.
= Timeline =
We now adopt a fixed cut-off date scheme. We will release twice a
year. The upcoming $RELEASE_VERSION timeline are as followed:
* Last posting date: $RELEASE_CUTOFF
* Hard code freeze: $RELEASE_FREEZE
* RC1: TBD
* Release: $RELEASE_DATE
Note that we don't have freeze exception scheme anymore. All patches
that wish to go into $RELEASE_VERSION must be posted no later than the last posting
date. All patches posted after that date will be automatically queued
into next release.
RCs will be arranged immediately after freeze.
We recently introduced a jira instance to track all the tasks (not only big)
for the project. See: https://xenproject.atlassian.net/projects/XEN/issues.
Most of the tasks tracked by this e-mail also have a corresponding jira task
referred by XEN-N.
I have started to include the version number of series associated to each
feature. Can each owner send an update on the version number if the series
was posted upstream?
= Projects =
EOF
POST=`mktemp`
cat <<EOF > $POST
EOF
# Preamble
cat $PRE
rm $PRE
# Body
cat $FILE | awk -f $AWK_FILE
rm $AWK_FILE
rm $FILE
cat $POST
rm $POST